For the past five years, RWA has served as Engineer of Record for Bonita Springs Utilities, Inc., and has successfully completed numerous utility design projects under this contract. These projects consisted of the design, permitting, and construction phases of multiple sanitary sewer force main and water main relocations. The construction administration services included project administration, bidding, construction services and spot inspections, testing and permit certification, as-built preparation, pay estimates, and project closeout.
Strike Lane RO Plant Raw Water Main & Transmission Main
RWA provided design, permitting, bidding, and construction phase services for an HDPE raw water transmission main, varying in size from 20” to 30” in diameter, from an existing raw water main at the intersection of Strike Lane and Three Oaks Parkway to the water treatment plant on East Terry Street. The transmission main was necessary for the future well-field expansion along Three Oaks Parkway. The project consisted of 17,000 feet of transmission main constructed in the median of Three Oaks Parkway, including multiple directional drills for road and culvert crossings. RWA was responsible for coordination with Lee DOT, SFWMD, the roadway design engineer, and various utility contractors for the project design. This project is awaiting budgetary funding for construction.
Windsor Road CFPD Water Tank Rezoning
RWA provided planning services for the rezoning of agricultural land to Community Facilities Planned Development for a two million gallon potable water storage tank, control building, and City of Bonita Springs park on the adjacent property. RWA also provided engineering, and surveying services for the design of the stormwater management system, paving, and grading on the water storage tank site as well as 800 feet of 12” water main replacement serving the water storage tank. RWA was responsible for coordination with the environmental consultant, landscape architect, and the City of Bonita Springs for the master planning of a passive park adjacent to the potable water storage tank site. RWA also provided lot split and lot combination services to create the water storage tank parcel. The water storage tank is currently under construction with completion anticipated in December 2008.
Coconut Square Master Lift Station
RWA provided design, permitting, bidding, and construction phase services for a master lift station located within the Coconut Square project which included dual 24” force mains from the proposed master lift station to connect to the existing 24” force main located on U.S. 41. The design was based on the existing flows generated by the systems connected to the existing 24” force main, as well as proposed development north of Coconut Road that will connect to the proposed force main. The total project involved approximately 1,200 feet of 12” force main and 800 feet of 24” force main, including two 24” directional bores under U.S. 41, most of which was constructed along the U.S. 41 corridor in advance of the road widening project recently completed by FDOT. RWA was responsible for coordination with the roadway design engineer, other utility providers, and FDOT during the design of the force main and master lift station.
Bonita Country Club System Upgrade - Bonita Pines
RWA provided the design and permitting services for a lift station replacement and gravity sanitary sewer replacement within the existing Bonita Pines development. The project included gravity collection for areas off-site in accordance with the Bonita Country Club Wastewater System Evaluation Report. The lift station was designed to allow for expansion to the areas south and east of Bonita Pines. Water main upgrades and replacements were also necessary as part of the gravity expansion design. The project included 8,200 feet of gravity sewers and 5,800 feet of potable water main. This project has been permitted and is awaiting resolution of assessments for the affected property owners prior to construction.
BSU Old 41 Utility Relocates Phase 2
RWA provided the design, permitting, bidding, and construction phase services for multiple sanitary sewer force main and water main relocations necessitated by improvements associated with the Old 41 Road Widening Project being constructed by the City of Bonita Springs. Sanitary force mains and water mains of various sizes were located within existing rights-of-way and easements along Old 41 Road from Rosemary Drive to U.S. 41. A major component of the utility relocation work was coordination with the roadway design engineer, as well as the proposed utility relocation plans of the private utilities within the existing right-of-way. A preliminary review of the 60 percent roadway design plans indicated a total of twenty significant water main and force main relocations. In addition, approximately 28 minor relocations were verified at specific locations during the design process through the use of subsurface utility locating. The project involved the relocation of more than 11,000 feet of force mains and water mains ranging in size from 8” through 24”. This project included coordination with the City of Bonita Springs Old 41 Road project design engineer, construction manager, and Seminole Gulf Coast Railroad.
Spring Creek Village Water & Sewer Study
RWA performed a water and sewer study that consisted of preparing proposed alternatives for replacing the existing water and sewer facilities within Spring Creek Village. The study consisted of assembling existing as-built water and sewer plans, reviewing existing studies and agreements, and obtaining copies of existing permits and consent orders. In addition, the study developed typical cross sections, explored three alternatives for the sanitary system, minimizing sizes of gravity, force and vacuum mains, developed a preliminary plan for potable water main replacement, reviewed restrictions for tying into the existing sanitary sewer system, developed an opinion of probable cost for feasible sewer alternatives and water mains, incorporated soil boring information, identified surveying needs, and developed preliminary and final construction budgets and schedules. The study required significant coordination with a geotechnical engineer in developing feasible alternatives for the sanitary sewer system replacement. Gravity, low pressure force main, and vacuum system options were reviewed. An opinion of probable cost was developed for each alternative and used for basis of assessments. The project involved conceptual planning of 8,000 feet of water main and gravity sanitary sewer.
Old 41 Shangrila Road Effluent Main & Force Main
RWA provided the design, permitting, bidding, and construction phase services for a new 30" ductile iron pipe effluent main, 8" PVC force main and a 4” communication conduit from the West Water Reclamation Facility (WWRF) south along Old 41 Road to Shangrila Road, running east and crossing I-75 to the East Water Reclamation Facility (EWRF). Coordination was necessary with the roadway engineers designing the Old 41 Road widening, Shangrila Road improvements, Three Oaks Parkway, the I-75 widening project, Seminole Gulf Railroad, and the consultant designing and building the EWRF. The total length of the project was 19,000 feet including the design of directional bores in two different locations. The longest of the bores was 600 feet long under I-75 involving three separate bores, one for each main; the 30” HDPE effluent main inside a 42” HDPE casing, 8” HDPE force main inside a 16” HDPE casing, and 4” HDPE communication line inside an 8” HDPE casing. The I-75 directional bores involved coordination with FDOT and the contractor constructing the EWRF. A second directional bore was 400 feet long under Old 41 Road and within the existing WWRF grounds involving three separate bores, one for each main; the 30” HDPE effluent main, 8” HDPE force main, and 4” HDPE communication line. The Old 41 Road directional bores involved coordination with Seminole Gulf Railroad and the City of Bonita Springs.
Bonita Pines Drainage Improvements
RWA provided the design and permitting services for approximately 5,000 feet of roadside drainage improvements within the existing Bonita Pines development, including Binky Lane, Tarrah Lane, and Corzine Road. The goal of the project was to restore historical flow ways and eliminate standing water issues. The project involved coordination with an adjacent roadway improvement project and the City of Bonita Springs.
Bonita Country Club Cypress Plantation Remediation
RWA provided the design, permitting, bidding, and construction phase services for a lift station replacement within the existing Bonita Country Club development. The project involved force main and pump station design.
Northgate MLS and Force Main
RWA provided the design, permitting, and bidding services for a water main and force main expansion project along North Commons Boulevard from Pelican Colony Boulevard to Coconut Road. This project involved the design of 2,000 feet of 8" sanitary force main to connect existing force mains to a new master lift station and 350 feet of 10" water main to create additional water main looping. The project involved coordination with Lee DOT, the City of Bonita Springs, and other private utilities. Other services provided included subsurface utility location to identify potential gas and electrical facility conflicts. This project is awaiting budgetary funding for construction.
Signal Road Water Main Loop
RWA provided the design, permitting, and bidding services for a water main looping project along Signal Road. This project involved the design of 800 feet of 12" water main to create additional water main looping, including a 200 foot directional bore under a Seminole Gulf Railroad crossing. The project involved coordination with Seminole Gulf Railroad, the City of Bonita Springs, and other private utilities. This project is awaiting budgetary funding for construction.
Collier Water Main Interconnect
RWA provided the design, permitting, and bidding services for a water main interconnect between Bonita Springs Utilities and Collier County Public Utilities. The project involved the design of 650 feet of 12” water main from the entrance to Vasari County Club south along the Imperial Parkway right-of-way to the Lee County/Collier County line. The improvements were required to provide emergency relief to either Bonita Springs Utilities, Inc. or Collier County Utilities. The project involved coordination with Collier County Public Utilities and their design engineer responsible for the interconnect assembly. This project is awaiting budgetary funding for construction.
East Bonita Beach Road Force Main Upgrade
RWA provided the design and permitting services for a force main upgrade project along Bonita Beach Road between Bonita Grande Drive and the entrance to Palmira Golf and Country Club. The project involved the design of 7,800 feet of 16” sanitary sewer force main, 110 feet of 10” sanitary sewer force main, and 560 feet of 6” sanitary sewer force main to replace the existing 8” sanitary sewer force main. The project involved extensive coordination with the roadway engineer designing the Bonita Beach Road widening project and Lee DOT. This project is currently in permitting.
Hickory Boulevard Force Main Upgrade
RWA provided the design and permitting services for a force main upgrade project along Hickory Boulevard between Forester Drive and the entrance to the Beach and Tennis Club condominiums. The project involved the design of 1,570 feet of 12” force main to replace the existing 8” force main and 140 feet of 4” force main. The project involved extensive coordination with Lee DOT.
Estero Boulevard Bridges Water Main Replacement
RWA performed an evaluation of the existing water mains attached to the bridges spanning Little Carlos Pass, New Pass, and Big Hickory Pass and provided replacement alternatives to Bonita Springs Utilities. The evaluation involved the investigation of the existing pipe and bridge conditions and the preparation of above and below ground replacement alternatives. Conceptual replacement plans were developed to prepare a preliminary opinion of probable cost for the evaluation of the alternative water main replacement designs. An evaluation report was prepared to present to the water main replacement alternatives and associated costs to Bonita Springs Utilities. The project involved coordination with Lee DOT and a local structural Engineer.